Table 11 Comparison of maintenance activities’ order in the reference and passenger flow peak scenarios

From: A data-driven prioritisation framework to mitigate maintenance impact on passengers during metro line operation

ID asset

Asset category

Station

Maintenance order (reference scenario)

Maintenance order (passenger flow peak scenario)

A060

Track circuit

BIGNAMI M5

1

8

A070

Track circuit

GARIBALDI M5

8

5

A065

Track circuit

ISTRIA M5

11

13

A088

Track circuit

SAN SIRO STADIO M5

10

3

A071

Track circuit

MONUMENTALE M5

20

9

A076

Track circuit

TRE TORRI M5

6

15

A059

Switch

BIGNAMI M5

9

7

A598

Switch

BIGNAMI M5

18

11

A701

Switch

GARIBALDI M5

12

2

A653

Switch

ISTRIA M5

3

6

A605

Wayside antenna

BIGNAMI M5

4

18

A083

Wayside antenna

SAN SIRO STADIO M5

19

20

A319

Platform door

BICOCCA M5

14

14

A608

Platform door

BIGNAMI M5

13

17

A644

Platform door

CA GRANDA M5

2

1

A746

Platform door

DOMODOSSOLA M5

5

10

A785

Platform door

LOTTO M5

16

16

A673

Platform door

MARCHE M5

15

12

A829

Signalling equipment room

SAN SIRO STADIO M5

17

19

A758

Signalling equipment room

TRE TORRI M5

7

4